nerdexam
BCS-ISEB

ISEB-PM1 · Question #5

ISEB-PM1 Question #5: Real Exam Question with Answer & Explanation

Sign in or unlock ISEB-PM1 to reveal the answer and full explanation for question #5. The question stem and answer options stay visible for context.

Question

A project manager has finished the project. He knows that the project scope has been completed ISEB ISEB-PM1 Exam and is within cost and time objectives set by management. Management, however, says that the project is a failure, because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was 33 weeks, the project is a success because:

Options

  • AIt only had six weeks of changes.
  • BIt was completed within the baseline.
  • CThere were so few changes.
  • DThere was good communication control.

Unlock ISEB-PM1 to see the answer

You've previewed enough free ISEB-PM1 questions. Unlock ISEB-PM1 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full ISEB-PM1 Practice