A project manager has finished the project. He knows that the project scope has been completed ISEB ISEB-PM1 Exam and is within cost and time objectives set by management. Management, however, says…

The correct answer is B. It was completed within the baseline. Option B is correct because a project baseline is the approved, official plan against which project performance is measured - if the baseline was set at 33 weeks and the project finished in 33 weeks, it met its baseline by definition, making it a success regardless of earlier…

Project Control

Question

A project manager has finished the project. He knows that the project scope has been completed ISEB ISEB-PM1 Exam and is within cost and time objectives set by management. Management, however, says that the project is a failure, because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was 33 weeks, the project is a success because:

Options

  • AIt only had six weeks of changes.
  • BIt was completed within the baseline.
  • CThere were so few changes.
  • DThere was good communication control.

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    79% (23)
  • C
    7% (2)
  • D
    3% (1)

Explanation

Option B is correct because a project baseline is the approved, official plan against which project performance is measured - if the baseline was set at 33 weeks and the project finished in 33 weeks, it met its baseline by definition, making it a success regardless of earlier estimates.

Why the distractors fail:

  • A is wrong because "six weeks of changes" is a fabricated detail - the question never mentions change volume, and quantity of changes doesn't determine success.
  • C is wrong for the same reason; the number of changes is irrelevant and not discussed in the scenario.
  • D is wrong because communication control is not what's being evaluated here - baseline adherence, not communication quality, is the success criterion in question.

Memory tip: Think of the baseline as the project's "official contract with management." Once approved, the original estimate (27 weeks) becomes history - the baseline (33 weeks) is the new target. If you hit the baseline, you win; if you beat a pre-baseline estimate, that's irrelevant.

Topics

#project baseline#project success criteria#schedule management