BCS-ISEB
ISEB-PM1 · Question #5
ISEB-PM1 Question #5: Real Exam Question with Answer & Explanation
Sign in or unlock ISEB-PM1 to reveal the answer and full explanation for question #5. The question stem and answer options stay visible for context.
Question
A project manager has finished the project. He knows that the project scope has been completed ISEB ISEB-PM1 Exam and is within cost and time objectives set by management. Management, however, says that the project is a failure, because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was 33 weeks, the project is a success because:
Options
- AIt only had six weeks of changes.
- BIt was completed within the baseline.
- CThere were so few changes.
- DThere was good communication control.
Unlock ISEB-PM1 to see the answer
You've previewed enough free ISEB-PM1 questions. Unlock ISEB-PM1 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.