A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews. The project is 40 percent complete and has used 60 percent of the available calendar…
The correct answer is D. Identify activities that required more time than planned. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews. The project is 40 percent complete and has used 60 percent of the available calendar time. What is the FIRST thing you should do?
Options
- ARebaseline the schedule to reflect the new date.
- BAnalyze the critical path activities for potential to fast track or crash the schedule.
- CDocument the lack of progress and associated issues to management.
- DIdentify activities that required more time than planned.
How the community answered
(26 responses)- A12% (3)
- B8% (2)
- C4% (1)
- D77% (20)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#schedule delays#root cause analysis#corrective action#project recovery