The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know how long the project will take if only nine resources each month are committed to your project. What is this activity called?

Options

  • ACrashing
  • BFloating
  • CLeveling
  • DFast tracking

How the community answered

(53 responses)
  • A
    8% (4)
  • B
    4% (2)
  • C
    74% (39)
  • D
    15% (8)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#resource leveling#resource constraints#schedule techniques