ISEB-PM1 · Question #31
While reviewing project performance, the project manager determines that the schedule variance is -500. What is the BEST thing to do?
The correct answer is B. Determine the cost variance. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
While reviewing project performance, the project manager determines that the schedule variance is -500. What is the BEST thing to do?
Options
- ALet the sponsor know.
- BDetermine the cost variance.
- CLook for activities that can be done in parallel.
- DMove resources from the project to one that is not failing.
How the community answered
(32 responses)- A13% (4)
- B78% (25)
- C3% (1)
- D6% (2)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#schedule variance#earned value management#corrective action#project performance