nerdexam
BCS-ISEB

ISEB-PM1 · Question #31

While reviewing project performance, the project manager determines that the schedule variance is -500. What is the BEST thing to do?

The correct answer is B. Determine the cost variance. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

While reviewing project performance, the project manager determines that the schedule variance is -500. What is the BEST thing to do?

Options

  • ALet the sponsor know.
  • BDetermine the cost variance.
  • CLook for activities that can be done in parallel.
  • DMove resources from the project to one that is not failing.

How the community answered

(32 responses)
  • A
    13% (4)
  • B
    78% (25)
  • C
    3% (1)
  • D
    6% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#schedule variance#earned value management#corrective action#project performance

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice