To accommodate a new project in your department, you need to move resources from one project to another. Because your department is currently working at capacity, moving resources will inevitably…
The correct answer is A. Project A with a benefit cost ratio of 0.8, no project charter, and four resources. You've hit your session limit · resets 10:20pm (America/New_York)
Resource Management
Question
To accommodate a new project in your department, you need to move resources from one project to another. Because your department is currently working at capacity, moving resources will inevitably delay the project from which you move the resources. It would cause the LEAST negative impact if you move resources from which of the following projects?
Options
- AProject A with a benefit cost ratio of 0.8, no project charter, and four resources
- BProject B with a net present value of $60,000, 12 resources, and variable costs between US
- CProject C with an opportunity cost of US $300,000, no project control plan, and an internal rate
- DProject D with indirect costs of US $20,000 and 13 resources
How the community answered
(55 responses)- A73% (40)
- B13% (7)
- C5% (3)
- D9% (5)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#resource allocation#benefit cost ratio#project prioritization#portfolio management