Which type of tool would be used for the quality planning activity?

The correct answer is D. Cost-Benefit Analysis. Cost-Benefit Analysis is the correct tool for quality planning because it is explicitly listed in the PMBOK as a technique for the Plan Quality Management process - it helps project managers weigh the cost of implementing quality activities against the benefits of meeting…

Quality Management

Question

Which type of tool would be used for the quality planning activity?

Options

  • ASchedule Analysis
  • BChecklist Analysis
  • CAssumption Analysis
  • DCost-Benefit Analysis

How the community answered

(57 responses)
  • A
    4% (2)
  • B
    16% (9)
  • C
    7% (4)
  • D
    74% (42)

Explanation

Cost-Benefit Analysis is the correct tool for quality planning because it is explicitly listed in the PMBOK as a technique for the Plan Quality Management process - it helps project managers weigh the cost of implementing quality activities against the benefits of meeting quality requirements, justifying where to invest in quality.

Why the distractors are wrong:

  • A. Schedule Analysis belongs to schedule management processes, not quality planning.
  • B. Checklist Analysis is a tool for the Identify Risks process; while checklists can be an output of quality planning, checklist analysis itself is not a quality planning tool.
  • C. Assumption Analysis is also a tool for Identify Risks, used to examine project assumptions for potential risk exposure.

Memory tip: Think "Quality costs money - so you analyze whether it's worth it before you plan it." Cost-Benefit Analysis is the only option that directly asks "is this worth doing?" - which is exactly the question you answer during quality planning, before you commit resources.

Topics

#quality planning#cost-benefit analysis#quality tools#planning activities