ISEB-PM1 · Question #257
Which type of tool would be used for the quality planning activity?
The correct answer is D. Cost-Benefit Analysis. Cost-Benefit Analysis is the correct tool for quality planning because it is explicitly listed in the PMBOK as a technique for the Plan Quality Management process - it helps project managers weigh the cost of implementing quality activities against the benefits of meeting…
Question
Which type of tool would be used for the quality planning activity?
Options
- ASchedule Analysis
- BChecklist Analysis
- CAssumption Analysis
- DCost-Benefit Analysis
How the community answered
(57 responses)- A4% (2)
- B16% (9)
- C7% (4)
- D74% (42)
Explanation
Cost-Benefit Analysis is the correct tool for quality planning because it is explicitly listed in the PMBOK as a technique for the Plan Quality Management process - it helps project managers weigh the cost of implementing quality activities against the benefits of meeting quality requirements, justifying where to invest in quality.
Why the distractors are wrong:
- A. Schedule Analysis belongs to schedule management processes, not quality planning.
- B. Checklist Analysis is a tool for the Identify Risks process; while checklists can be an output of quality planning, checklist analysis itself is not a quality planning tool.
- C. Assumption Analysis is also a tool for Identify Risks, used to examine project assumptions for potential risk exposure.
Memory tip: Think "Quality costs money - so you analyze whether it's worth it before you plan it." Cost-Benefit Analysis is the only option that directly asks "is this worth doing?" - which is exactly the question you answer during quality planning, before you commit resources.