nerdexam
BCS-ISEB

ISEB-PM1 · Question #222

How is scheduled variance calculated using the earned value technique?

The correct answer is C. EV less PV. Scheduled Variance (SV) = Earned Value (EV) minus Planned Value (PV), which is option C. SV measures whether you're ahead or behind schedule in cost terms: a positive result means you've accomplished more work than planned, while a negative result means you're behind. Why the…

Project Control

Question

How is scheduled variance calculated using the earned value technique?

Options

  • AEV less AC
  • BAC less PV
  • CEV less PV
  • DAC less EV

How the community answered

(16 responses)
  • A
    19% (3)
  • B
    6% (1)
  • C
    69% (11)
  • D
    6% (1)

Explanation

Scheduled Variance (SV) = Earned Value (EV) minus Planned Value (PV), which is option C. SV measures whether you're ahead or behind schedule in cost terms: a positive result means you've accomplished more work than planned, while a negative result means you're behind.

Why the distractors are wrong:

  • A (EV − AC) is the formula for Cost Variance (CV) - it measures budget efficiency, not schedule performance.
  • B (AC − PV) has no standard EVM meaning and mixes actual spending with planned spending without reference to what was actually accomplished.
  • D (AC − EV) is simply the inverse of Cost Variance - also not a recognized EVM metric.

Memory tip: Think of "SV" as comparing two Values - EV vs PV - both sharing the word "value." Cost Variance is the odd one out that introduces Actual Cost (AC) into the mix. If you can remember "Schedule Variance = two Vs," you'll never confuse it with CV again.

Topics

#schedule variance#earned value#SV calculation#EV vs PV

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice