ISEB-PM1 · Question #222
How is scheduled variance calculated using the earned value technique?
The correct answer is C. EV less PV. Scheduled Variance (SV) = Earned Value (EV) minus Planned Value (PV), which is option C. SV measures whether you're ahead or behind schedule in cost terms: a positive result means you've accomplished more work than planned, while a negative result means you're behind. Why the…
Question
How is scheduled variance calculated using the earned value technique?
Options
- AEV less AC
- BAC less PV
- CEV less PV
- DAC less EV
How the community answered
(16 responses)- A19% (3)
- B6% (1)
- C69% (11)
- D6% (1)
Explanation
Scheduled Variance (SV) = Earned Value (EV) minus Planned Value (PV), which is option C. SV measures whether you're ahead or behind schedule in cost terms: a positive result means you've accomplished more work than planned, while a negative result means you're behind.
Why the distractors are wrong:
- A (EV − AC) is the formula for Cost Variance (CV) - it measures budget efficiency, not schedule performance.
- B (AC − PV) has no standard EVM meaning and mixes actual spending with planned spending without reference to what was actually accomplished.
- D (AC − EV) is simply the inverse of Cost Variance - also not a recognized EVM metric.
Memory tip: Think of "SV" as comparing two Values - EV vs PV - both sharing the word "value." Cost Variance is the odd one out that introduces Actual Cost (AC) into the mix. If you can remember "Schedule Variance = two Vs," you'll never confuse it with CV again.
Topics
Community Discussion
No community discussion yet for this question.