nerdexam
BCS-ISEB

ISEB-PM1 · Question #223

The project management processes presented in the PMBOK Guide should:

The correct answer is C. Be selected as appropriate by the project team. Option C is correct because the PMBOK Guide explicitly states that its processes are not prescriptive - the project team is responsible for tailoring and selecting which processes are appropriate for the specific project, based on its size, complexity, and context. Why the…

Organizational Aspects of Project Management

Question

The project management processes presented in the PMBOK Guide should:

Options

  • AAlways be applied uniformly
  • BBe selected as appropriate by the sponsor
  • CBe selected as appropriate by the project team
  • DBe applied based on ISO guidelines.

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    78% (29)
  • D
    14% (5)

Explanation

Option C is correct because the PMBOK Guide explicitly states that its processes are not prescriptive - the project team is responsible for tailoring and selecting which processes are appropriate for the specific project, based on its size, complexity, and context.

Why the distractors are wrong:

  • A is wrong because applying all processes uniformly to every project would be inefficient; the PMBOK Guide is a framework, not a one-size-fits-all mandate.
  • B is wrong because process selection is a technical/execution responsibility that belongs to the project team, not the sponsor (whose role is funding and strategic oversight).
  • D is wrong because PMBOK is a PMI standard, not an ISO standard - there is no ISO guideline that governs PMBOK process selection.

Memory tip: Think of it as "the people doing the work decide the tools" - the team tailors the methodology. The sponsor defines the "why," the team defines the "how."

Topics

#PMBOK processes#process tailoring#process groups#project team responsibility

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice