nerdexam
BCS-ISEB

ISEB-PM1 · Question #221

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods? ISEB…

The correct answer is B. EAC. EAC (Estimate at Completion) is the correct forecasting metric because it represents the expected total cost of the project upon completion, combining actual costs spent to date with a revised estimate for remaining work - exactly what a sponsor needs for a mid-project cost…

Project Control

Question

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods? ISEB ISEB-PM1 Exam

Options

  • ABAC
  • BEAC
  • CETC
  • DWBS

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    76% (16)
  • C
    14% (3)
  • D
    5% (1)

Explanation

EAC (Estimate at Completion) is the correct forecasting metric because it represents the expected total cost of the project upon completion, combining actual costs spent to date with a revised estimate for remaining work - exactly what a sponsor needs for a mid-project cost forecast.

Why the others are wrong:

  • A. BAC (Budget at Completion) is the original approved total budget, not a forecast - it doesn't account for how the project is actually performing.
  • C. ETC (Estimate to Complete) only covers the remaining work cost from the current point forward, not the total project cost.
  • D. WBS (Work Breakdown Structure) is a planning tool that decomposes project scope into deliverables - it's not a cost forecasting metric at all.

Memory tip: Think of the acronyms as a timeline - BAC is where you planned to end up, ETC is what's left to spend, and EAC is the full picture ("A to C" = start to finish). When a sponsor asks "what will this project cost in total?", you need the full picture: EAC.

Topics

#estimate at completion#EAC#cost forecasting#earned value

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice