As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication should be required for this effort?

The correct answer is C. Written. Written communication (C) is correct because imposing a standard method requires documentation that subordinates can reference repeatedly, follow consistently, and be held accountable to - verbal or informal communication cannot enforce a repeatable standard across a team…

Communication Management

Question

As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication should be required for this effort?

Options

  • AAll of the other alternatives apply.
  • BFace-to-face
  • CWritten
  • DNon-verbal
  • ETelephone

How the community answered

(27 responses)
  • A
    19% (5)
  • B
    7% (2)
  • C
    70% (19)
  • E
    4% (1)

Explanation

Written communication (C) is correct because imposing a standard method requires documentation that subordinates can reference repeatedly, follow consistently, and be held accountable to - verbal or informal communication cannot enforce a repeatable standard across a team. Face-to-face (B) and telephone (E) are real-time, undocumented exchanges that leave no authoritative record and are impractical for distributing a methodology to multiple people uniformly. Non-verbal (D) cannot convey the procedural detail required for a cost-calculation standard. "All of the above" (A) is wrong because only written communication fulfills the key requirements of this scenario: permanence, clarity, and enforceability.

Memory tip: When a question involves standards, policies, or procedures - anything that must be followed consistently over time - think written. If it disappears when the conversation ends, it can't be a standard.

Topics

#written communication#downward communication#standards enforcement#cost management