Which of the following are outputs of the Perform Integrated Change control process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is B. Project management plan update C. Project document update D. Change request status update. See the full explanation below for the reasoning.

Question

Which of the following are outputs of the Perform Integrated Change control process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AWork performance information
  • BProject management plan update
  • CProject document update
  • DChange request status update

How the community answered

(56 responses)