GIAC
GCPM · Question #93
to build up an estimate of the monetary resources required to complete project activities?
The correct answer is C. Estimate costs. See the full explanation below for the reasoning.
Question
to build up an estimate of the monetary resources required to complete project activities?
Options
- ADetermine budget
- BControl costs
- CEstimate costs
- DPlan quality
How the community answered
(41 responses)- A7% (3)
- B2% (1)
- C78% (32)
- D12% (5)
Community Discussion