GIAC
GCPM · Question #91
GCPM Question #91: Real Exam Question with Answer & Explanation
The correct answer is C. $800. See the full explanation below for the reasoning.
Question
hours have been spent and the estimate to complete is 1 additional hour. The project must have been completed already. An hourly rate of $100 per hour is provided. Which of the following is the planned value (PV) for the project?
Options
- A$500
- B$700
- C$800
- D$600
Community Discussion
No community discussion yet for this question.