nerdexam
GIAC

GCPM · Question #91

GCPM Question #91: Real Exam Question with Answer & Explanation

The correct answer is C. $800. See the full explanation below for the reasoning.

Question

hours have been spent and the estimate to complete is 1 additional hour. The project must have been completed already. An hourly rate of $100 per hour is provided. Which of the following is the planned value (PV) for the project?

Options

  • A$500
  • B$700
  • C$800
  • D$600

Community Discussion

No community discussion yet for this question.

Full GCPM Practice