GIAC
GCPM · Question #91
hours have been spent and the estimate to complete is 1 additional hour. The project must have been completed already. An hourly rate of $100 per hour is provided. Which of the following is the…
The correct answer is C. $800. See the full explanation below for the reasoning.
Question
hours have been spent and the estimate to complete is 1 additional hour. The project must have been completed already. An hourly rate of $100 per hour is provided. Which of the following is the planned value (PV) for the project?
Options
- A$500
- B$700
- C$800
- D$600
How the community answered
(43 responses)- A2% (1)
- B12% (5)
- C81% (35)
- D5% (2)
Community Discussion
No community discussion yet for this question.