What cost estimating approach uses the work breakdown structure to create a cost estimate?
The correct answer is B. Definitive. See the full explanation below for the reasoning.
Question
What cost estimating approach uses the work breakdown structure to create a cost estimate?
Options
- AAnalogous
- BDefinitive
- CParametric
- DTop down
How the community answered
(35 responses)- A6% (2)
- B77% (27)
- C3% (1)
- D14% (5)