nerdexam
GIAC

GCPM · Question #90

What cost estimating approach uses the work breakdown structure to create a cost estimate?

The correct answer is B. Definitive. See the full explanation below for the reasoning.

Question

What cost estimating approach uses the work breakdown structure to create a cost estimate?

Options

  • AAnalogous
  • BDefinitive
  • CParametric
  • DTop down

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    77% (27)
  • C
    3% (1)
  • D
    14% (5)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice