As a Project Manager, you are managing a project that has fourteen deliverables from outside vendors. One vendor has been in negotiations with a partner for more financing that could cause the…

The correct answer is A. Contact the vendor and discuss this problem. See the full explanation below for the reasoning.

Question

As a Project Manager, you are managing a project that has fourteen deliverables from outside vendors. One vendor has been in negotiations with a partner for more financing that could cause the vendor to stop production on one of your deliverables if they don?t reach an agreement. A rumor is out that the vendor's plant will be shutting down because of this issue. What is the best course of action you should take?

Options

  • AContact the vendor and discuss this problem
  • BStart contacting other vendors as a backup plan
  • CChange vendors as soon as one is found
  • DInitiate the risk response plan created for this vendor

How the community answered

(47 responses)
  • A
    81% (38)
  • B
    11% (5)
  • C
    4% (2)
  • D
    4% (2)