As a Project Manager, you are managing a project that has fourteen deliverables from outside vendors. One vendor has been in negotiations with a partner for more financing that could cause the…
The correct answer is A. Contact the vendor and discuss this problem. See the full explanation below for the reasoning.
Question
As a Project Manager, you are managing a project that has fourteen deliverables from outside vendors. One vendor has been in negotiations with a partner for more financing that could cause the vendor to stop production on one of your deliverables if they don?t reach an agreement. A rumor is out that the vendor's plant will be shutting down because of this issue. What is the best course of action you should take?
Options
- AContact the vendor and discuss this problem
- BStart contacting other vendors as a backup plan
- CChange vendors as soon as one is found
- DInitiate the risk response plan created for this vendor
How the community answered
(47 responses)- A81% (38)
- B11% (5)
- C4% (2)
- D4% (2)