GCPM · Question #81

You are a Project Manager at Dewey, Cheatum, and Howe and assigned to a major construction project. The project is on schedule and under budget, but you are constantly in conflict with a member of…

The correct answer is C. Reporting this problem to senior management with a solution of replacing this team member. See the full explanation below for the reasoning.

Question

You are a Project Manager at Dewey, Cheatum, and Howe and assigned to a major construction project. The project is on schedule and under budget, but you are constantly in conflict with a member of your project team. This team member is sabotaging the project. What would be the best solution to resolve this problem?

Options

  • AFiring the team member from the project as soon as possible
  • BReporting this to senior management
  • CReporting this problem to senior management with a solution of replacing this team member
  • DHolding a team meeting to vote if the team member should be removed

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    84% (21)
  • D
    8% (2)