GIAC
GCPM · Question #81
You are a Project Manager at Dewey, Cheatum, and Howe and assigned to a major construction project. The project is on schedule and under budget, but you are constantly in conflict with a member of…
The correct answer is C. Reporting this problem to senior management with a solution of replacing this team member. See the full explanation below for the reasoning.
Question
You are a Project Manager at Dewey, Cheatum, and Howe and assigned to a major construction project. The project is on schedule and under budget, but you are constantly in conflict with a member of your project team. This team member is sabotaging the project. What would be the best solution to resolve this problem?
Options
- AFiring the team member from the project as soon as possible
- BReporting this to senior management
- CReporting this problem to senior management with a solution of replacing this team member
- DHolding a team meeting to vote if the team member should be removed
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C84% (21)
- D8% (2)