You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You know that developers are available in your…

The correct answer is B. Make or buy analysis. See the full explanation below for the reasoning.

Question

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You know that developers are available in your organization, and would like to use them. However, your program manager thinks that an outside company needs to be engaged to complete this development. Which of the following will help you to convince your project manager to use the internal resources?

Options

  • AExpert Judgment
  • BMake or buy analysis
  • CSurvey Questionnaire
  • DIssue log

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    74% (20)
  • C
    4% (1)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice