You have recently started a project and assembled the project team which has begun working on the project. However, recently, a project team member has expressed his concerns of having issues with…
The correct answer is A. Meet with both team members, assess the scenario, and be more directive in decision. See the full explanation below for the reasoning.
Question
You have recently started a project and assembled the project team which has begun working on the project. However, recently, a project team member has expressed his concerns of having issues with one of the other project team members, and cannot get him to collaborate. What is the MOST appropriate activity for you to do in this scenario?
Options
- AMeet with both team members, assess the scenario, and be more directive in decision
- BReplace the other project team member immediately with another suitable resource.
- CReallocate both team members different works so that there is no overlap, by resolving the
- DUpdate your PMO about the conflict and raise a project risk about team disruption.
How the community answered
(47 responses)- A79% (37)
- B11% (5)
- C4% (2)
- D6% (3)