The correct answer is C. Alan must add twelve hours of lag time to each of the 200 doors painting activity to. See the full explanation below for the reasoning.

Question

project. The office has 200 doors. All doors have to be glassed and painted. Before each door can be painted, the glasses must be fitted in them at least 12 hours before. Alan has arranged these tasks with a finish to start relationship between glassing and painting. What else should Alan do to account for the twelve hours of maintenance time?

Options

  • AAlan must add twelve hours of lead time to each of the 200 doors painting activity to
  • BAlan must schedule all 200 office doors to be glassed first and then schedule all 200 doors
  • CAlan must add twelve hours of lag time to each of the 200 doors painting activity to
  • DAlan must add an intermediary task with duration of twelve hours.