GCPM · Question #66

You are project manager of HHK project. Examine the network diagram given below: A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based…

The correct answer is B. Four days. See the full explanation below for the reasoning.

Question

You are project manager of HHK project. Examine the network diagram given below: A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

Options

  • AFive days
  • BFour days
  • CSix days
  • DZero, it is on the critical path.

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    84% (32)
  • C
    5% (2)
  • D
    8% (3)