GCPM · Question #61

Sasha is the project manager of a large construction project. She is finalizing ground rules, training, and team-building activities for her project team members. In which of the following processes…

The correct answer is C. Develop Project Team. See the full explanation below for the reasoning.

Question

Sasha is the project manager of a large construction project. She is finalizing ground rules, training, and team-building activities for her project team members. In which of the following processes is she working on?

Options

  • AManage Project Team
  • BDevelop Human Resource Plan
  • CDevelop Project Team
  • DAcquire Project Team

How the community answered

(15 responses)
  • A
    13% (2)
  • B
    7% (1)
  • C
    73% (11)
  • D
    7% (1)