GCPM · Question #60

James works as the project manager for a software project. He and his team are on the Direct and Manage Project Execution process. All of the following are inputs of this process except for which one?

The correct answer is A. Project charter. See the full explanation below for the reasoning.

Question

James works as the project manager for a software project. He and his team are on the Direct and Manage Project Execution process. All of the following are inputs of this process except for which one?

Options

  • AProject charter
  • BApproved environmental requests
  • COrganizational process assets
  • DEnterprise environmental factors
  • EProject management plan

How the community answered

(18 responses)
  • A
    83% (15)
  • C
    11% (2)
  • D
    6% (1)

Community Discussion

No community discussion yet for this question.