GCPM · Question #51
You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports…
The correct answer is C. Perform integrated change control process. See the full explanation below for the reasoning.
Question
You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?
Options
- AProject change control process
- BConfiguration management
- CPerform integrated change control process
- DCommunications management
How the community answered
(45 responses)- A4% (2)
- B9% (4)
- C73% (33)
- D13% (6)