GCPM · Question #50

Which of the following components of EVA is described in the statement below? "It is a measure of how much of the project value has been earned so far through completed work, that is, the budgeted…

The correct answer is D. EV. See the full explanation below for the reasoning.

Question

Which of the following components of EVA is described in the statement below? "It is a measure of how much of the project value has been earned so far through completed work, that is, the budgeted cost of the work that has been performed through the project status date."

Options

  • APV
  • BAC
  • CSV
  • DEV

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    4% (1)
  • D
    80% (20)