GCPM · Question #46
Which of the following are inputs of the Acquire Project Team process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is B. Organizational process assets C. Enterprise environmental factors D. Project management plan. See the full explanation below for the reasoning.
Question
Which of the following are inputs of the Acquire Project Team process? Each correct answer represents a complete solution. Choose all that apply.
Options
- AResource calendars
- BOrganizational process assets
- CEnterprise environmental factors
- DProject management plan
How the community answered
(44 responses)- A23% (10)
- B77% (34)
Community Discussion
No community discussion yet for this question.