Which of the following processes formally permits the initiation of a project and marks the kickoff for all consequent development activities to begin?

The correct answer is B. Develop project charter. See the full explanation below for the reasoning.

Question

Which of the following processes formally permits the initiation of a project and marks the kickoff for all consequent development activities to begin?

Options

  • ADevelop project scope statement
  • BDevelop project charter
  • CDevelop project team
  • DDevelop project management plan

How the community answered

(38 responses)
  • A
    11% (4)
  • B
    82% (31)
  • C
    3% (1)
  • D
    5% (2)