Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don was to perform a risk audit, who would carry the risk in this scenario?
The correct answer is C. Don would because of the contract type. See the full explanation below for the reasoning.
Question
Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don was to perform a risk audit, who would carry the risk in this scenario?
Options
- AJerry would because he is the hired contractor.
- BDon would because he is the project manager.
- CDon would because of the contract type.
- DJerry would because of the contract type.
How the community answered
(27 responses)- A11% (3)
- B4% (1)
- C81% (22)
- D4% (1)