GCPM · Question #387
You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at…
The correct answer is D. 0.93. See the full explanation below for the reasoning.
Question
You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
Options
- A1.06
- B-$30,647
- C0.92
- D0.93
How the community answered
(43 responses)- A9% (4)
- B2% (1)
- C5% (2)
- D84% (36)