GCPM · Question #367
Which of the following tasks are NOT part of the project execution phase? Each correct answer represents a complete solution. Choose two.
The correct answer is A. Making an expected resources list C. Creating a baseline schedule. See the full explanation below for the reasoning.
Question
Which of the following tasks are NOT part of the project execution phase? Each correct answer represents a complete solution. Choose two.
Options
- AMaking an expected resources list
- BReviewing issues tracking logs
- CCreating a baseline schedule
- DReviewing a schedule baseline
How the community answered
(23 responses)- A78% (18)
- B13% (3)
- D9% (2)
Community Discussion