Which of the following tasks are NOT part of the project execution phase? Each correct answer represents a complete solution. Choose two.

The correct answer is A. Making an expected resources list C. Creating a baseline schedule. See the full explanation below for the reasoning.

Question

Which of the following tasks are NOT part of the project execution phase? Each correct answer represents a complete solution. Choose two.

Options

  • AMaking an expected resources list
  • BReviewing issues tracking logs
  • CCreating a baseline schedule
  • DReviewing a schedule baseline

How the community answered

(23 responses)
  • A
    78% (18)
  • B
    13% (3)
  • D
    9% (2)