administration. Holly, the team leader of a project, provides Jane the performance indexes of her project. The schedule variance (SV) of her project is 15. What does this figure illustrate?

The correct answer is A. Holly's project is ahead of the schedule. See the full explanation below for the reasoning.

Question

administration. Holly, the team leader of a project, provides Jane the performance indexes of her project. The schedule variance (SV) of her project is 15. What does this figure illustrate?

Options

  • AHolly's project is ahead of the schedule.
  • BHolly's project is behind the schedule.
  • CHolly's project has costs that are higher than planned.
  • DHolly's project is right on target.

How the community answered

(20 responses)
  • A
    75% (15)
  • B
    15% (3)
  • C
    5% (1)
  • D
    5% (1)