Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent…
The correct answer is C. .80. See the full explanation below for the reasoning.
Question
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?
Options
- A1.23
- B$524,000
- C.80
- D100 percent because the vendor caused her lateness
How the community answered
(51 responses)- A16% (8)
- B8% (4)
- C73% (37)
- D4% (2)