GCPM · Question #355
Which of the following is an input to the Identify Risk process?
The correct answer is A. The project scope statement. See the full explanation below for the reasoning.
Question
Which of the following is an input to the Identify Risk process?
Options
- AThe project scope statement
- BResidual risks
- CReturn on investment
- DReferent power
How the community answered
(47 responses)- A77% (36)
- B15% (7)
- C6% (3)
- D2% (1)