nerdexam
GIAC

GCPM · Question #343

GCPM Question #343: Real Exam Question with Answer & Explanation

The correct answer is B. The project will be late by six days.. See the full explanation below for the reasoning.

Question

the project's critical path. You have calculated that one of the activities on the critical path is going to be delayed by six days due to a vendor fault. How will this condition affect the project's completion date?

Options

  • AThe project may be late depending on the amount of float available for the critical path.
  • BThe project will be late by six days.
  • CThe project will be early by six days.
  • DThe project manager should check to see if float is available for other activities and shift

Community Discussion

No community discussion yet for this question.

Full GCPM Practice