Which of the following is defined as the time it takes to complete a task or a set of interdependent tasks?

The correct answer is D. Lead time. See the full explanation below for the reasoning.

Question

Which of the following is defined as the time it takes to complete a task or a set of interdependent tasks?

Options

  • ALag time
  • BMean time
  • CFixed time
  • DLead time

How the community answered

(43 responses)
  • A
    12% (5)
  • B
    5% (2)
  • C
    5% (2)
  • D
    79% (34)