GCPM · Question #293
Mark works as a project manager for the SLQ Project. He is working with the project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and…
The correct answer is B. System or process flow chart. See the full explanation below for the reasoning.
Question
Mark works as a project manager for the SLQ Project. He is working with the project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique will Mark use to achieve the above task?
Options
- APredecessor and successor diagramming
- BSystem or process flow chart
- CInfluence diagram
- DCause and effect diagram
How the community answered
(46 responses)- A11% (5)
- B83% (38)
- C4% (2)
- D2% (1)
Community Discussion