Mark works as a project manager for the SLQ Project. He is working with the project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and…

The correct answer is B. System or process flow chart. See the full explanation below for the reasoning.

Question

Mark works as a project manager for the SLQ Project. He is working with the project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique will Mark use to achieve the above task?

Options

  • APredecessor and successor diagramming
  • BSystem or process flow chart
  • CInfluence diagram
  • DCause and effect diagram

How the community answered

(46 responses)
  • A
    11% (5)
  • B
    83% (38)
  • C
    4% (2)
  • D
    2% (1)

Community Discussion