Which of the following is built by aggregating the costs of the individual work elements and then joining them at time intervals where meaningful actual cost information will be available?

The correct answer is A. Cost baseline. See the full explanation below for the reasoning.

Question

Which of the following is built by aggregating the costs of the individual work elements and then joining them at time intervals where meaningful actual cost information will be available?

Options

  • ACost baseline
  • BCost estimation
  • CCost controlling
  • DCost budgeting

How the community answered

(40 responses)
  • A
    85% (34)
  • B
    3% (1)
  • C
    5% (2)
  • D
    8% (3)