nerdexam
GIAC

GCPM · Question #242

Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement…

The correct answer is D. Look-up table. See the full explanation below for the reasoning.

Question

Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?

Options

  • ARisk management plan
  • BRisk response plan
  • CProject sponsor
  • DLook-up table

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    4% (1)
  • C
    9% (2)
  • D
    78% (18)