GCPM · Question #242
Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement…
The correct answer is D. Look-up table. See the full explanation below for the reasoning.
Question
Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?
Options
- ARisk management plan
- BRisk response plan
- CProject sponsor
- DLook-up table
How the community answered
(23 responses)- A9% (2)
- B4% (1)
- C9% (2)
- D78% (18)