GCPM · Question #241
break the project into small, individual, and manageable components. Which of the following tasks will you perform in the above scenario?
The correct answer is B. Create WBS. See the full explanation below for the reasoning.
Question
break the project into small, individual, and manageable components. Which of the following tasks will you perform in the above scenario?
Options
- ACreate a Gantt chart.
- BCreate WBS.
- CCreate an activity diagram.
- DCreate a PERT chart.
How the community answered
(16 responses)- A6% (1)
- B81% (13)
- C13% (2)