GCPM · Question #24
You are in need of procuring several tons of pea gravel for a construction. You'll need the vendor to provide a bid for the pea gravel on a specific date and time and that's one of the requirements…
The correct answer is D. The buyer. See the full explanation below for the reasoning.
Question
You are in need of procuring several tons of pea gravel for a construction. You'll need the vendor to provide a bid for the pea gravel on a specific date and time and that's one of the requirements included in the procurement document package you are reviewing. Who creates the procurement document package?
Options
- AThe project sponsor
- BBoth parties contribute
- CThe seller
- DThe buyer
How the community answered
(33 responses)- A15% (5)
- B3% (1)
- C9% (3)
- D73% (24)