GIAC
GCPM · Question #23
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an…
The correct answer is B. Work breakdown structure. See the full explanation below for the reasoning.
Question
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
Options
- AProject scope
- BWork breakdown structure
- CCode of accounts
- DProject management plan
How the community answered
(35 responses)- A17% (6)
- B71% (25)
- C3% (1)
- D9% (3)
Community Discussion
No community discussion yet for this question.