two activities. He wants to delay the start of the second activity by 14 hours. Which of the following scheduling components will Jeff add to the second activity?
The correct answer is C. Lag time. See the full explanation below for the reasoning.
Question
two activities. He wants to delay the start of the second activity by 14 hours. Which of the following scheduling components will Jeff add to the second activity?
Options
- AProject slack
- BProject float
- CLag time
- DLead time
How the community answered
(39 responses)- A10% (4)
- B5% (2)
- C82% (32)
- D3% (1)