nerdexam
GIAC

GCPM · Question #186

two activities. He wants to delay the start of the second activity by 14 hours. Which of the following scheduling components will Jeff add to the second activity?

The correct answer is C. Lag time. See the full explanation below for the reasoning.

Question

two activities. He wants to delay the start of the second activity by 14 hours. Which of the following scheduling components will Jeff add to the second activity?

Options

  • AProject slack
  • BProject float
  • CLag time
  • DLead time

How the community answered

(39 responses)
  • A
    10% (4)
  • B
    5% (2)
  • C
    82% (32)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice