GCPM · Question #185

ideas, tasks, dependencies, and associations with team members. Which of the following will help you to achieve the above task?

The correct answer is C. Organizational chart. See the full explanation below for the reasoning.

Question

ideas, tasks, dependencies, and associations with team members. Which of the following will help you to achieve the above task?

Options

  • AStakeholders register
  • BProject charter
  • COrganizational chart
  • DRisk register

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    8% (2)
  • C
    73% (19)
  • D
    4% (1)