GIAC
GCPM · Question #172
hours have been spent and the estimate to complete is an additional hour. The project should have been completed already. An hourly rate of $100 per hour is provided, and the project is 91.7%…
The correct answer is B. 0.67. See the full explanation below for the reasoning.
Question
hours have been spent and the estimate to complete is an additional hour. The project should have been completed already. An hourly rate of $100 per hour is provided, and the project is 91.7% complete. Which of the following is the correct CPI for the project?
Options
- A0.86
- B0.67
- C0.45
- D0.53
How the community answered
(35 responses)- A3% (1)
- B86% (30)
- C3% (1)
- D9% (3)
Community Discussion
No community discussion yet for this question.