Mark works as a project manager for the SLQ Project. He is working with the project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and…

The correct answer is D. System or process flow chart. See the full explanation below for the reasoning.

Question

Mark works as a project manager for the SLQ Project. He is working with the project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique will Mark use to achieve the above task?

Options

  • AInfluence diagram
  • BCause and effect diagram
  • CPredecessor and successor diagramming
  • DSystem or process flow chart

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    4% (1)
  • D
    83% (20)