The correct answer is A. It categorizes the tasks that can be delayed for a while if resources need to be reallocated B. It determines both the early start and the late start date for each activity in the schedule. C. It identifies the tasks that should be completed on time for the whole project to be. See the full explanation below for the reasoning.
Question
Which of the following are the prime reasons behind the use of the Critical path method in a project? Each correct answer represents a complete solution. Choose all that apply.
Options
- AIt categorizes the tasks that can be delayed for a while if resources need to be reallocated
- BIt determines both the early start and the late start date for each activity in the schedule.
- CIt identifies the tasks that should be completed on time for the whole project to be
- DIt is used to describe the maximum length of time needed to complete a project.