GCPM · Question #168
Charlie has just completed the project according to the terms of the contract. She and the customer are completing a walk through of the project deliverables, and the customer is asking for changes…
The correct answer is A. Perform integrated change control. See the full explanation below for the reasoning.
Question
Charlie has just completed the project according to the terms of the contract. She and the customer are completing a walk through of the project deliverables, and the customer is asking for changes to the deliverables before she'll accept the product. What project management Mprocess should manage the documented change request that may come from scope verification?
Options
- APerform integrated change control
- BControl Scope
- CControl change control
- DScope management
How the community answered
(34 responses)- A71% (24)
- B18% (6)
- C9% (3)
- D3% (1)