Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process? Each correct answer represents a complete solution…
The correct answer is B. Scope baseline C. Project documents D. Risk management plan. See the full explanation below for the reasoning.
Question
Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process? Each correct answer represents a complete solution. Choose all that apply.
Options
- ARisk register
- BScope baseline
- CProject documents
- DRisk management plan
How the community answered
(36 responses)- A28% (10)
- B72% (26)