GCPM · Question #120

Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process? Each correct answer represents a complete solution…

The correct answer is B. Scope baseline C. Project documents D. Risk management plan. See the full explanation below for the reasoning.

Question

Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • ARisk register
  • BScope baseline
  • CProject documents
  • DRisk management plan

How the community answered

(36 responses)
  • A
    28% (10)
  • B
    72% (26)

Community Discussion

No community discussion yet for this question.