GCPM · Question #119

At which of the following points in a project lifecycle is the level of uncertainty and risk the highest?

The correct answer is C. Beginning. See the full explanation below for the reasoning.

Question

At which of the following points in a project lifecycle is the level of uncertainty and risk the highest?

Options

  • APlanning
  • BClosing
  • CBeginning
  • DMonitoring

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    14% (5)
  • C
    74% (26)
  • D
    3% (1)