Input from other Service Management processes is required to keep the IT service continuity plan current. Which process has the most to contribute?
The correct answer is A. Change management. See the full explanation below for the reasoning.
Question
Input from other Service Management processes is required to keep the IT service continuity plan current. Which process has the most to contribute?
Options
- AChange management
- BAvailability management
- CFinancial management for IT services
- DProblem management
How the community answered
(49 responses)- A80% (39)
- B6% (3)
- C12% (6)
- D2% (1)