EX0-112 · Question #34
Which Management process is responsible for monitoring how many hours have been worked?
The correct answer is C. Planning and resource management. Planning and Resource Management is responsible for monitoring hours worked because it oversees the allocation, scheduling, and tracking of resources - including human effort (time/hours) - to ensure work aligns with project plans and capacity. Contract Management (A) deals…
Question
Which Management process is responsible for monitoring how many hours have been worked?
Options
- AContract management
- BFinancial management
- CPlanning and resource management
How the community answered
(43 responses)- A2% (1)
- B7% (3)
- C91% (39)
Explanation
Planning and Resource Management is responsible for monitoring hours worked because it oversees the allocation, scheduling, and tracking of resources - including human effort (time/hours) - to ensure work aligns with project plans and capacity.
Contract Management (A) deals with negotiating, executing, and administering contracts with vendors or clients; it governs legal and commercial obligations, not internal time tracking. Financial Management (B) handles budgets, costs, and financial reporting - while labor costs may feed into it, the monitoring of hours worked is a resource management function, not a financial one.
Memory tip: Think of the phrase "Planning who does what and for how long" - the word "long" (duration/hours) ties directly to Planning and Resource Management, since people (resources) are what you measure hours against.